File #: 23-067    Version: 2 Name: Request City Council to: (1) Adopt Resolution No. ____ Amending the 2022-2023 Fiscal Budget Appropriating $XXX from the Fund , Account No. XXX-XXX-XXXX for the “SR-210/ Alder Avenue Interchange Improvement Project, City Project No. 200808”; (2) Award a Co
Type: Agenda Item Status: Approved
File created: 1/12/2023 In control: City Council
On agenda: 1/24/2023 Final action: 1/24/2023
Title: Request City Council to: (1) Adopt Resolution No. 8042 Amending the 2022-2023 Fiscal Budget and Appropriating $3.2 Million from the RSP/EIR Fair Share Agreement Fund 301 for the "SR-210/Alder Avenue Interchange Improvement Project, City Project No. 200808"; (2) Award a Construction Contract to Ortiz Enterprises, Inc. in the Amount of $5,767,076.25; and (3) Authorize the City Manager to Execute all Documents. (ACTION)
Attachments: 1. Attachment 1 - Bid Summary.pdf, 2. Attachment 2 - Disclosures.pdf, 3. Attachment 3 - Agreement.pdf, 4. Attachment 4 - Notice of Exemption.pdf, 5. Budget Resolution.pdf

For City Council Meeting [January 24, 2023]

TO:                                          Honorable Mayor and City Council

APPROVAL:                     Arron Brown, Acting City Manager

FROM:                     Alberto Paiva, P.E., Director of Engineering Services/City Engineer

 

Title

Request City Council to: (1) Adopt Resolution No. 8042 Amending the 2022-2023 Fiscal Budget and Appropriating $3.2 Million from the RSP/EIR Fair Share Agreement Fund 301 for the “SR-210/Alder Avenue Interchange Improvement Project, City Project No. 200808”; (2) Award a Construction Contract to Ortiz Enterprises, Inc. in the Amount of $5,767,076.25; and (3) Authorize the City Manager to Execute all Documents.

(ACTION)

Body

BACKGROUND:

On March 11, 2014, the City Council Adopted Resolution Establishing a Fair Share Traffic Mitigation Fee for projects developed in the Renaissance Specific Plan (RSP) Area. The Fee study estimates the improvement requirements necessary at build-out of the RSP, including improvements at the SR-210/Alder Avenue Interchange.

 

Additionally, traffic studies for various industrial projects area (e.g., Panattoni I-210 III - V, Thrifty Oil, ProLogis, Monster, etc…) within the Renaissance Specific Plan (RSP) area have identified certain deficiencies of the SR-210 Alder Avenue interchange. The Transportation Commission conditioned each of these development projects to pay certain fair share fees to make minor improvements to the east bound and west bound Alder Avenue on and off ramps to mitigate impacts caused by their projects. The traffic studies indicated that other improvements of the Alder Avenue interchange, including but not limited to widening the bridge structure might be necessary to accommodate the future planned growth in the City. More recently, the Traffic Impact Analysis prepared for the proposed Amendment to the Renaissance Specific Plan/Environmental Impact Report (EIR) also concluded that the Alder Interchange might not accommodate cumulative traffic volumes.

 

Based upon direction received from the Transportation Commission, on November 22, 2016, the City Council approved a Reimbursement Agreement with Lewis-Hillwood Rialto Company (“LHR”) to reimburse costs associated with a new City-initiated public project: SR- 210 / Alder Avenue Interchange Improvement Project (the “Project”). At that time, the City Council approved $275,000 to proceed with a feasibility study of the Project with the goal of improving traffic circulation and movement of trucks at the Interchange. The City and LHR selected Advanced Civil Technologies (“ACT”) as the design firm for the Project.

 

The existing roadway system along Alder Avenue does not provide sufficient turning and through movements onto State Route 210 and intersections in the immediate vicinity to serve forecasted 2040 travel demands. ACT completed a Feasibility Study which analyzed short-term and long-term improvements required at the Interchange to accommodate current and future traffic volumes at build-out in 2040.

 

The findings of the Feasibility Study recommended:

 

1)                      Widening southbound Alder Avenue to include a right turn lane onto the westbound on-ramp;

2)                      Restriping to add a second left turn lane onto Renaissance Parkway;

3)                      Restriping to add a second left turn lane onto the WB on-ramp;

4)                      Adding a shared thru lane;

5)                      Widening of northbound Alder Avenue to provide right turn lanes onto Casmalia Street and the eastbound on-ramp;

6)                      Restriping Alder Avenue to add a second left turn lane onto Casmalia Street;

7)                      Widening westbound off-ramp to provide a second left turn lane;

8)                      Widening eastbound off-ramp to provide a right turn lane.

 

On February 12, 2019, the City Council approved an amendment to the Reimbursement Agreement with LHR to proceed with Phase II of the Project - preparation of a Preliminary Engineering Evaluation Report (PEER). At that time, the City Council was provided a copy of the Feasibility Study that had been reviewed by the California Department of Transportation (“Caltrans”) that owns and maintains the Interchange. Preparation of the PEER for review and approval by Caltrans was the next step in the Project.

 

On November 10, 2020, the City Council approved an amendment to the Reimbursement Agreement with LHR to proceed with Phase III of the Project - preparation of final Plans, Specifications and Estimate (PSE) for the Project. At that time the City Council also appropriated $3,936,250 in funding for the construction phase.

 

On June 14, 2022, the City Council authorized a purchase order in the amount of $871,224 with Prescience Corporation pursuant to the City’s “On-Call” Agreement for Construction Management, Inspection, and Materials Testing Services for the SR-210/Alder Avenue Interchange Improvement Project, City Project 200808. Through this approval, Prescience Corporation completed constructability review of the project plans.

At this meeting, the City Council also approved the final design and authorized construction advertisement for bidding.

 

ANALYSIS/DISCUSSION:

On December 08, 2022, the City released RFB No. 23-025 for SR-210/ Alder Avenue Interchange Improvement Project, City Project No. 200808, and published the Notice Inviting Bids on the PlanetBids.com website.

 

On January 10, 2023 the City received three (3) bids, tabulated in Table 1 below:

 

1.                     Ortiz Enterprises, Inc., Irvine, CA:                                                                                                         $5,767,076.25

2.                     Riverside Construction Company, Inc., Riverside, CA:                                          $7,073,097.70

3.                     Beador Construction Company, Inc., Costa Mesa, CA:                                          $7,186,700.00

 

A full bid summary is included as Attachment 1.  The engineer’s estimate provided by the developer’s design team was $4,300,000.  The lowest responsible and responsive bid was $5,767,076 submitted by Ortiz Enterprises, Inc. Costs are significantly higher than the engineer’s estimate reflecting the escalation in material costs and material delays. Staff reviewed the bid and found Ortiz Enterprises, Inc. to be properly licensed and qualified. 

 

A copy of the Disclosure Statement, Contractor’s License and DIR verification documents are included as Attachment 2.  Staff recommends that the City Council accept the bid received from Ortiz Enterprises. as the lowest responsible and responsive bid. A construction contract with Ortiz Enterprises Inc. for the project is included as Attachment 3.

 

The project is currently funded by RSP/EIR Fair Share Agreement funds in the amount of $5.1 million of which $3.2 million was appropriated for the construction costs. With the bids coming in higher than estimated, additional budget appropriations will be required to accommodate additional budget for construction costs.

 

The current fund balance for RSP/EIR Fair Share Agreement Fund 301 is estimated at $10.7 million. Staff recommends that the original budget for the project be revised and appropriate an additional $3.2 million from Fund 301 fund balance for the construction costs.

 

ENVIRONMENTAL IMPACT:

Section 21084 of the California Public Resources Code requires that the guidelines for implementation of the California Environmental quality (CEQA) include a list of classes of projects that have been determined not to have a significant effect on the environment and which shall, therefore, be exempt from the provisions of CEQA. In response to that mandate, the Secretary for Resources identified classes of projects that do not have a significant effect on the environment and are declared categorically exempt from the requirement for the preparation of environmental documents. In accordance with 14 CCR Section 15301 “Existing Facilities”, Class 1 projects consist of the repair, maintenance, or minor alteration of existing structures and facilities; therefore, the SR- 210/Alder Avenue Interchange Improvement Project, Project No. 200808 is considered categorically exempt from CEQA. Staff will file a Notice of Exemption for the project, included as Attachment 4.

 

GENERAL PLAN CONSISTENCY:

This action is consistent with Guiding Principle 3A in the General Plan:

Our City government will lead by example, and will operate in an open, transparent, and responsive manner that meets the needs of the citizens and is a good place to do business.

 

Approval of this action also complies with the following City of Rialto General Plan Goals and Policies:

 

Goal 3-11:                      Provide community facilities that adequately support established programs, can accommodate future needs, and are accessible to all members of the community.

 

Goal 3-11.1:                     Allocate resources for the maintenance and operations of City facilities; explore alternative funding options for maintenance and operational costs of new facilities.

 

Policy 4-1.1:                     Establish and maintain standards for a variety of street classifications to  serve both local and regional traffic, including Major Arterial Highways, Major Arterials, Secondary Arterials, Collector Streets, and Local Streets.

 

LEGAL REVIEW:

The City Attorney has reviewed and supports this staff report.

 

FINANCIAL IMPACT:

Operating Budget Impact

The proposed action will not affect the Operating Budget.

 

Capital Improvement Budget Impact

The currently adopted project budget for the SR-210/ Alder Avenue Interchange Project, City Project No. 200808 is $5,128,309 within the RSP/EIR Fair Share Agreement Fund Account No. 301-500-4312-2011 and 301-500-4312-3001.

 

Expended and encumbered to date is $2,363,349, leaving a remaining project budget balance of $ 2,764,960 in the RSP/EIR Fair Share Agreement Fund, Account No. 301-500-4312-3001-200808.

 

Staff recommends that the City Council consider appropriating an additional $3.2 from RSP/EIR Fair Share Agreement Fund balance to accommodate an additional budget for the construction contract.

 

After the adoption of the requested Budget Resolution the construction contract award with Ortiz Enterprises, Inc. in the amount of $5,767,076.25 will be funded from the RSP/EIR Fair Share Agreement Fund, Account No. 301-500-4312-3001-200808-05.

 

Licensing

A Business License Tax at the Professional Services rate in the amount of $5,829 based on the construction amount of $5,767,076.25 will be paid by Ortiz Enterprises, Inc. prior to commencing the services for this project. 

 

RECOMMENDATION:

Staff recommends that City Council:

 

•                     Adopt a Resolution Amending the 2022-2023 Fiscal Budget Appropriating $3.2 Million from the RSP/EIR Fair Share Agreement Fund 301 for the “SR-210/ Alder Avenue Interchange Improvement Project, City Project No. 200808;

•                     Award a Construction Contract to Ortiz Enterprises, Inc. in the amount of $5,767,076.25.

•                     Authorize the Acting City Manager to Execute all Documents.