For City Council Meeting [January 24, 2023]
TO: Honorable Mayor and City Council
APPROVAL: Arron Brown, Acting City Manager
FROM: Alberto Paiva, P.E., Director of Engineering Services/City Engineer
Title
Request City Council to: (1) Delegate Additional Authority for Change Orders in the Cumulative Amount of $850,000 to Calmex Engineering Inc., a California Corporation for the Street Overlay & Reconstruction Project, City Project No. 180807; (2) Appropriate an additional $550,000 for additional Rialto Police Patrol; (3) Approve the Second Amendment to the Professional Services Agreement with Southstar Engineering and Consulting, Inc. in the amount of $297,860 for Construction Management Services; (4) Adopt Resolution No. 8041 Amending the 2022-2023 Fiscal Budget Appropriating an additional $500,000 to the Project Budget; and (5) Authorize the City Manager to Execute all Related Documents.
(ACTION)
Body
BACKGROUND:
On May 10, 2022, the City Council awarded a Construction Contract to Calmex Engineering Inc., a California corporation, in the amount of $9,736,123.06 for the Street Overlay & Reconstruction Project, City Project No. 180807. The City Council also requested for overtime to Rialto Police to be adjusted and billed against the project for additional patrol during nighttime construction.
ANALYSIS/DISCUSSION:
On May 10, 2022, at the time of the award of the Construction contract, the City Council delegated $480,000 in authority to the City Manager to approve change orders at the time of the construction contract award. The City utilized the funds to construct deep lift asphalt intersections to mitigate impacts to the industrial and commercial businesses south of the I-10.
The original scope of work involved “Full Depth Reclamation” in which the entire asphalt pavement is ground in place and mixed with dry cement as Cement Stabilized Treated Base. The process requires 10 days of work and curing time prior to the placement of asphalt. The project is also being phased with the removal of exterior lanes first and removal of interior lanes second. This process further extends the required time for reconstruction of the full width of the street. Construction of deep-lift asphalt pavement will provide a life cycle similar to Full Depth Reclamation but is more expensive per square foot basis. However, the benefit has drastically reduced the period of time for construction in those areas.
Staff is recommending an appropriation of $850,000 for two (2) new right turn lanes at Santa Ana Avenue and Resource Drive from southbound Riverside Avenue and additional unforeseen circumstances. Adding the right turn lanes at this phase of the construction project will reduce additional impacts to the community and avoid developers from constructing against the City’s moratorium and cutting into the newly constructed roadway. The new right turn lanes will provide better queuing and turning clearances for truck traffic. Approval of additional work requires City Council action given that the initial $480,000 in change order authority will be exceeded.
A cooperative agreement will be prepared with each developer to assign the developers their obligation to the City to incorporate the improvement as part of the City Project with the condition that each developer pays the City its fair share of the estimated cost of the improvements.
Additionally, at the May 10, 2022 Council meeting, the City Council recommended adjusting the project budget to allow Rialto PD to have additional patrols on South Riverside during the overnight work. The project budget allocated $300,000 for Rialto PD overtime, which has since been exhausted. Staff is recommending an additional appropriation of $550,000 to provide nighttime patrol until the end of the construction project which is estimated to be completed at the end of March 2023.
Construction Management Support Services
On September 14, 2021, the City Council authorized a contract to Southstar Engineering and Consulting, Inc. in the total amount of $1,243,369 with $100,000.00 of the amount available for constructability review and public outreach. The remaining balance was to be authorized by an amendment to the agreement subject to future City Council approval.
On May 10, 2022, the City Council approved the remaining balance to Southstar’s contract in the amount of $1,143,369 as part of the first amendment to Southstar’s PSA.
Staff is recommending the approval of a second amendment to extend construction management and inspection services for the addition of two (2) new right turn lanes at Santa Ana Avenue and Resource Drive from southbound Riverside Avenue in the amount of $297,860. The Second Amendment to Southstar’s PSA and a copy of the Disclosure Statement is included as Attachment 1 & 2, respectively.
ENVIRONMENTAL IMPACT:
Section 21084 of the California Public Resources Code requires that the guidelines for implementation of the California Environmental quality (CEQA) include a list of classes of projects that have been determined not to have a significant effect on the environment and which shall, therefore, be exempt from the provisions of CEQA. In response to that mandate, the Secretary for Resources identified classes of projects that do not have a significant effect on the environment and are declared categorically exempt from the requirement for the preparation of environmental documents. In accordance with 14 CCR Section 15301 “Existing Facilities”, Class 1 projects consist of the repair, maintenance, or minor alteration of existing structures and facilities; therefore, the 2020/2021 Street Overlay & Reconstruction Project, City Project No. 180807 is considered categorically exempt from CEQA. Staff has prepared and filed a Notice of Exemption for the project.
GENERAL PLAN CONSISTENCY:
This action is consistent with Guiding Principle 3A in the General Plan:
Our City government will lead by example, and will operate in an open, transparent, and responsive manner that meets the needs of the citizens and is a good place to do business.
Approval of this action also complies with the following City of Rialto General Plan Goals and Policies:
Goal 4-1: Provide transportation improvements to reduce traffic congestion associated with regional and local trip increases.
Policy 4-1.1: Establish and maintain standards for a variety of street classifications to serve both local and regional traffic, including Major Arterial Highways, Major Arterials, Secondary Arterials, Collector Streets, and Local Streets.
LEGAL REVIEW:
The City Attorney has reviewed and supports this staff report and the Second Amendment.
FINANCIAL IMPACT:
Operating Budget Impact
The proposed action will not affect the Operating Budget.
Capital Improvement Budget Impact
The currently adopted project budget for the Street Overlay & Reconstruction Project, City Project No. 180807 is $12,296,000 within the following funds:
• Measure I Fund, Account Number 201-500-4310-3001 in the amount of $5,196,000
• Gas Tax Fund, Account Number 202-500-4317-3001 in the amount of $1,400,000
• Gas Tax SB1 Fund, Account Number 203-500-7305-3001 in the amount of $5,700,000
Expended and encumbered to date is $11,418,916.47, leaving a remaining project budget balance of $720,943in the Measure I Fund, Account No. 201-500-4310-3001-180807-05 and $156,140 in the Gas Tax Fund, Account No. 203-500-7305-3001-180807-35.
Staff recommends that the City Council consider appropriating an additional $850,000 to the project budget for the Construction Contract Change orders, Police efforts to patrol the night work performed, and the amendment with Southstar Engineering.
A budget resolution to amend the 2022/2023 fiscal budget to increase an expenditure appropriation in the Measure I fund, Account No. 201-500-4310-3001-180807-05 in the amount of $500,000. The remaining funds needed in the amount of $350,000 are budgeted and available in the Major Capital Grants Project, Account No. 223-500-4414-3001-180807-15.
RECOMMENDATION:
Staff recommends that the City Council:
• Delegate Additional Authority for Change Orders in the Cumulative Amount of $850,000 to Calmex Engineering Inc., a California Corporation for the Street Overlay & Reconstruction Project, City Project No. 180807;
• Appropriate an additional $550,000 for additional Rialto Police Patrol;
• Approve the Second Amendment to the Professional Services Agreement with Southstar Engineering and Consulting, Inc. in the amount of $297,860 for Construction Management Services;
• Adopt a Resolution Amending the 2022-2023 Fiscal Budget Appropriating an additional $500,000 to the Project Budget;
• Authorize the City Manager to Execute all Related Documents.