Legislation Details

File #: WS-24-1258    Version: 1 Name:
Type: Agenda Item Status: Agenda Ready
File created: 3/18/2024 In control: Water Subcommittee
On agenda: 3/27/2024 Final action:
Title: Water and Wastewater Rate Study. RECOMMENDATION Request that the Water Subcommittee provide feedback on Water and Wastewater Rate Model. (ACTION)
Attachments: 1. Amendment 1 Water and Wastewater Rate Study 03072024.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

FOR: Water Subcommittee Meeting [March 27, 2024]

TO: Honorable Water Subcommittee Members

APPROVAL:                     Stephen Dopudja, P.E., Interim Utilities Manager

Toyasha Sebbag, Assistant to the City Manager 

 

...Title

Water and Wastewater Rate Study.

 

RECOMMENDATION

Request that the Water Subcommittee provide feedback on Water and Wastewater Rate Model. (ACTION)

 

...Body

BACKGROUND

The agenda includes a discussion and presentation during the meeting by F.G. Solutions, the City's Water and Wastewater Consultant, regarding the ongoing development of the updated rate model.

 

ANALYSIS/DISCUSSION

At the February 27, 2024, City Council Meeting staff requested that the item pertaining to a public hearing under Proposition 218 to adjust water and wastewater rates be tabled until a future date to be determined. It was further explained that City staff would bring back for City Council consideration to set a new public hearing with new and proper 218 notification materials.

 

Subsequently, staff requested a 2023 Water and Wastewater Rate Study Amendment 1 (ATTACHMENT 1) to a professional services agreement with FG Solutions, LLC with a timeline to update rate calculations with rates effective January 1, 2025, 2026, 2027, 2028, and 2029. Below is the proposed milestone schedule:

 

Proposed Milestones

Date

Notice to Proceed

03/08/2024

Draft Rate Proposal to City Staff

03/26/2024

Water Subcommittee Meeting

03/27/2024

Attend Various Meetings

TBD

Final Rate Proposal Developed

04/09/2024

Council Sets Proposition 218 Hearing

04/23/2024

Preliminary Draft Report Delivered

05/16/2024

Final Draft Report Delivered

05/31/2024

Proposition 218 Public Hearing

06/25/2024

1st Rate Adjustment

01/01/2025

 

Any requirement to produce more than one iteration of a rate proposal will result in delay of all scheduled milestones.

 

FINANCIAL IMPACT

Operating Budget

Funds are available in water and wastewater contract services operating accounts, with funds split based on the number of accounts served.

 

The 2023 Water and Wastewater Rate Study Amendment 1 costs will be split as follows:

Water with approximately 12,500 (37%) accounts

$24,291

Wastewater with approximately 21,470 (63%) accounts

$41,360

Amendment 1 Costs

$65,651

 

The Original Professional Services Agreement (PSA) awarded on April 11, 2023, was for $138,297. The PSA Amendment 1 is for $65,651, bringing the total contract cost to $203,948. Amendment 1 is within the signature authority of Arron Brown, Assistant City Manager because it is for under $100,000 and did not need to return to the City Council for authorization.

 

Capital Improvement Budget

The proposed action will not impact the Capital Improvement Budget.