Skip to main content
File #: WS-25-0594    Version: 1 Name:
Type: Agenda Item Status: Agenda Ready
File created: 8/23/2025 In control: Water Subcommittee
On agenda: 9/18/2025 Final action:
Title: Update on the Biosolids Project at the Wastewater Treatment Plant Provided by RWS/Veolia's Management Team.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

For Water Subcommittee Meeting September 18, 2025

TO:                                           Water Subcommittee Members

APPROVAL:                      Tanya Williams, City Manager

FROM:                      Nicole Hemmans, Senior Administrative Analyst

 

Title

Update on the Biosolids Project at the Wastewater Treatment Plant Provided by RWS/Veolia’s Management Team.

 

Body

ANALYSIS/DISCUSSION:

Rialto Water Services (RWS) will present a progress update on the Biosolids Project following its approval by the City Council and the Rialto Utility Authority on August 12, 2025. This update includes key milestones related to design-build (DB) contract execution, procurement timelines, equipment manufacturing, and the overall project schedule through early 2026.

 

DB Contracts and Project Schedule

 

  • DB Contracts (Veolia, W.M. Lyles, AECOM) – in process, completion by August 27, 2025
  • Notification of procurement to equipment vendors – September 2, 2025
  • Purchase Orders issued – September 2025
  • Shop drawings (long-lead equipment) – October–December 2025
  • Manufacturing of long-lead equipment – Q1 2026 (January–February)
  • Design process to 100% completion – December 31, 2025
  • Mobilization – Q1 2026 (January 2026)
  • Equipment delivery – Q2 2026 (initiation of major onsite construction; construction activity tied closely to delivery schedule)

 