For Economic Development Committee [September 18, 2025]
TO: Honorable Economic Development Committee Members
APPROVAL: Christina Taylor, Community Development Director
FROM: Matt Bennett, City Engineer
Title
Update on Design of Residential Streets Rehabilitation - Zone 3 Phase I, City Project No. 26083 and Update on Design of Residential Streets Rehabilitation - Zone 3 Phase ll, City Project No. 26084.
Body
DISCUSSION
On May 27, 2025, the City Council approved the draft of the Fiscal Year 2026-2027 Five-Year Capital Improvement Plan. Approximately $6,400,000 was programmed for all phases of a pavement management program project for FY 2025-2026.
On June 10, 2025, the City Council adopted Resolution No. 8357, adopting a list of projects funded by Senate Bill 1: The Road Repair and Accountability Act of 2017 for Fiscal Year 2025/2026. From the list, Residential Streets Rehabilitation - Zone 3 Phase I & II, City Project No. 26083 & 26084 were identified to address an area of the City that has received numerous resident calls and requests for rehabilitation over the last several years.
On November 15, 2022, the City Council approved an on-call agreement with PSOMAS and Michael Baker for On-Call Professional Civil Engineering Services for an initial three (3) year term, with two (2) one (1) year optional extensions. PSOMAS submitted a cost proposal for Zone 3 Phase I, City Project No. 26083, to the City for the roadway rehabilitation design for the streets listed in Table 1 below. A map of the area is included as Attachment 1. Work generally includes roadway rehabilitation and construction of curb ramps to current standards.
Table 1 - Zone 3 Phase I
In addition, Michael Baker submitted a cost proposal for Zone 3 Phase II, City Project No. 26084 to the City for the roadway rehabilitation design for the streets listed in Table 2 below. A map of the area is included as Attachment 2. Work generally includes roadway rehabilitation and construction of curb r...