For Economic Development Committee March 27, 2025
TO: Honorable Economic Development Committee Members
APPROVAL: Colby Cataldi, Director of Community Development
FROM: Paul Gonzales, Community Development Manager
Title
Community Development - Private Development Project Updates
Body
ANALYSIS/DISCUSSION
Staff will provide a progress updates for the active entitlement projects in different phases of the development process. The projects to be discussed include but are not limited to the projects listed below.
a. Chick fil A Restaurant (NW Corner of Foothill Blvd. and Larch)
Engineering and Counsel preparing draft Developer Impact Fee agreements for both the mini storage and Chick fil A projects. It is estimated that Chick fil A could be under construction and opening in 2026.
b. Dutch Bros. Coffee (eastside of Riverside Ave south of Baseline Ave.)
Currently under building plan check review processes.
c. Best Western Plus (southside of Foothill Blvd. west of Cactus Ave.)
Currently under construction on Foothill Blvd. with anticipated completion of construction and opening by 4th quarter, 2025.
d. Beyond Food Mart (Riverside Ave. south of I-10 Fwy)
Currently under construction and resolving utility undergrounding design with SCE. Offsite improvements to follow upon completion of SCE utility work. Anticipated completion by 4th quarter, 2025.
e. Bridge / Pepper Industrial Project (Pepper Ave south of 210 Fwy)
Grading and building permits in process. Developer estimating to commence construction by June 2025.
f. Crow Industrial Project (northside of Baseline Ave. between Cedar and Cactus)
Grading and building permits in process.
RECOMMENDATION
Receive and File