For City Council Meeting May 26, 2026
TO: Honorable Mayor and City Council
FROM: Tanya Williams, City Manager
AUTHOR: Nicole Hemmans, Senior Administrative Analyst
Title
Request City Council/Rialto Utility Authority to: (1) Approve Contract Amendment No. 3 With Enplanners in the Amount of $11,155 for a Revised Total Not-To-Exceed Contract Amount of $271,741, for Additional Environmental Survey Services Associated With the Dr. June Hayes and Deborah Roberston Habitat Nature Center, Formally Known as the Rialto Habitat Nature Center (RHNC) Project; and (2) Authorize the City Manager/Executive Director or Their Designee to Execute all Related Documents.
Body
RECOMMENDATION
Staff recommends that the City Council/Rialto Utility Authority:
1) Approve Contract Amendment No. 3 with Enplanners in the amount of $11,155 for a revised total not-to-exceed contract amount of $271,741, for additional Environmental Survey Services associated with the Dr. June Hayes and Deborah Roberston Habitat Nature Center, formally known as the Rialto Habitat Nature Center (RHNC) Project; and
2) Authorize the City Manager/Executive Director or their designee to execute all related documents.
BACKGROUND
On June 15, 2022, the Rialto Utility Authority (RUA) entered into a Professional Services Agreement (PSA) with Enplanners, Inc. to provide environmental consulting services related to the preparation of an Initial Study/Mitigated Negative Declaration (IS/MND) and supporting technical studies for the RHNC project. Following the initial engagement, the Authority approved to expand the scope of services to support additional needs identified:
* Amendment No. 1 (September 12, 2023) expanded the scope of work to include additional CEQA Plus documentation, technical studies, and tribal consultation assistance associated with the RHNC Project.
* Amendment No. 2 (April 28, 2025) authorized additional regulatory permitting and processing services required to obtain approvals from resour...
Click here for full text