Title: Request City Council to: (1) Delegate Additional Authority for Change Orders in the Cumulative Amount of $850,000 to Calmex Engineering Inc., a California Corporation for the Street Overlay & Reconstruction Project, City Project No. 180807; (2) Appropriate an additional $550,000 for additional Rialto Police Patrol; (3) Approve the Second Amendment to the Professional Services Agreement with Southstar Engineering and Consulting, Inc. in the amount of $297,860 for Construction Management Services; (4) Adopt Resolution No. 8041 Amending the 2022-2023 Fiscal Budget Appropriating an additional $500,000 to the Project Budget; and (5) Authorize the City Manager to Execute all Related Documents. (ACTION)
Attachments: 1. Attachment 1 - Second Amendment to PSA with Southstar.pdf, 2. Attachment Budget Resolution.pdf
For City Council Meeting [January 24, 2023]
TO: Honorable Mayor and City Council
APPROVAL: Arron Brown, Acting City Manager
FROM: Alberto Paiva, P.E., Director of Engineering Services/City Engineer

Title
Request City Council to: (1) Delegate Additional Authority for Change Orders in the Cumulative Amount of $850,000 to Calmex Engineering Inc., a California Corporation for the Street Overlay & Reconstruction Project, City Project No. 180807; (2) Appropriate an additional $550,000 for additional Rialto Police Patrol; (3) Approve the Second Amendment to the Professional Services Agreement with Southstar Engineering and Consulting, Inc. in the amount of $297,860 for Construction Management Services; (4) Adopt Resolution No. 8041 Amending the 2022-2023 Fiscal Budget Appropriating an additional $500,000 to the Project Budget; and (5) Authorize the City Manager to Execute all Related Documents.
(ACTION)
Body
BACKGROUND:
On May 10, 2022, the City Council awarded a Construction Contract to Calmex Engineering Inc., a California corporation, in the amount of $9,736,123.06 for the Street Overlay & Reconstruction Project, City Project No. 180807. The City Council also requested for overtime to Rialto Police to be adjusted and billed against the project for additional patrol during nighttime construction.

ANALYSIS/DISCUSSION:
On May 10, 2022, at the time of the award of the Construction contract, the City Council delegated $480,000 in authority to the City Manager to approve change orders at the time of the construction contract award. The City utilized the funds to construct deep lift asphalt intersections to mitigate impacts to the industrial and commercial businesses south of the I-10.

The original scope of work involved "Full Depth Reclamation" in which the entire asphalt pavement is ground in place and mixed with dry cement as Cement Stabilized Treated Base. The process requires 10 days of work and curing time prior to the placement of asphalt. The project is also...

Click here for full text