Legislation Details

File #: WS-26-0367    Version: 1 Name:
Type: Agenda Item Status: Agenda Ready
File created: 5/21/2026 In control: Water Subcommittee
On agenda: 5/28/2026 Final action:
Title: Update on the Citywide Integrated Security Project (FILE AND RECEIVE)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

For Water Subcommittee Meeting May 28, 2026

TO:                                           Water Subcommittee Members

APPROVAL:                      Tanya Williams, City Manager

FROM:           Nicole Hemmans, Senior Administrative Analyst

 

Title

Update on the Citywide Integrated Security Project (FILE AND RECEIVE)

 

Body

BACKGROUND:

On July 22, 2025, the City Council authorized the release of bids for the Citywide Integrated Security Solutions Project, City Project No. 230102, which is intended to enhance the security and resiliency of the City’s water and wastewater facilities.

 

This project involves the construction and installation of security devices at various water and wastewater facilities throughout the city.  The general items of work to be performed include construction of perimeter fencing, communication towers, gate/access controls, security lighting, video/thermal imaging cameras, intrusion switches, audio alarms, flashing beacons, signage and other security measures as detailed in the construction documents.  The Engineer’s estimate is $4.8 million.

 

ANALYSIS/DISCUSSION

The following table outlines the chronology of events and current status of the project to date:

 

PROJECT TIMELINE

07/22/25                     City Council authorized the release of bids

02/17/26                     Project was advertised on Planet bids.com.

03/03/26                     Mandatory pre-bid meeting held.

04/02/26                     Deadline to submit bids after a 44-calendar day bid period. No bids were received.

04/17/26                     Project was re-advertised on Planetbids.com.

04/22/26                     Mandatory pre-bid meeting held.

05/21/26                     To date 38 questions have been received from bidders. 

06/15/26                     Deadline to submit bids

 

Following the review of the final bid submissions, a preliminary bid and contract recommendation will be brough to the Water Sub-Committee in June, with a recommendation for full contract award in July to the City Council.