Skip to main content
File #: EDC-25-0590    Version: 1 Name:
Type: Agenda Item Status: Agenda Ready
File created: 8/21/2025 In control: Economic Development Committee
On agenda: 8/28/2025 Final action:
Title: Update on upcoming Baseline Storm Drain Project, City Project No. 170700
Attachments: 1. Attachment 1 Tamarind to Cactus.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
For Economic Development Committee [August 28 2025]
TO: Honorable Economic Development Committee Members
APPROVAL: Christina Taylor, Director of Community Development
FROM: Matt Bennett, City Engineer

Title
Update on upcoming Baseline Storm Drain Project, City Project No. 170700

Body
DISCUSSION
In 2016, the San Bernardino County Flood Control District (SBCFCD) began development of the Cactus Basin System Improvements, which includes expanding the basins to increase storage capacity. On August 8, 2017, the City Council authorized staff to release a Request for Proposal for the design of the master-planned storm drain in Baseline Road from the Cactus Basin to Tamarind Avenue.

On June 26, 2018, the City Council awarded a professional services agreement to Huitt-Zollars Inc. for the design of the Baseline Master Plan Storm Drain from the Cactus Basin to Tamarind Avenue in the amount of $521,625.

On April 27, 2021, City Council adopted a mitigated negative declaration, approved a first amendment to the professional services agreement with Huitt-Zollars in the amount of $44,000 for a not-to-exceed amount of $565,625 for Phase 1 and authorized advertisement for construction bids for Phase 1 of the Baseline Storm Drain Project, City Project, 170700. The project was originally anticipated to be split into two phases to allow for the easement, encroachment permits, and regulatory permits to be obtained during construction in phase 1 in anticipation of phase 2. The project has since been combined into one continuous project.

On September 12, 2023, City Council approved Tentative Parcel Map No. 2020-0001, Resolution No. 8141 Conditional Development Permit No. 2020-0002, Resolution 8142 Precise Plan of Design No. 2020-00012 and Resolution No. 8143 Environmental Assessment Review No. 2020-0003 for the Crow Holdings Industrial development (APN:0264-213-18) located on the north side of Baseline Road approximately 350 feet east of Fitzgerald Avenue. Crow Holdings I...

Click here for full text