Conditional Development Permit No. 2017-0035: A request to allow the development of a 120,600 square foot distribution warehouse facility located at the northeast corner of Locust Avenue and Vineyard Avenue (APNs: 1133-201-01, -02 and -03) within the Planned Industrial Development (I-PID) zone of the Rialto Airport Specific Plan & Variance No. 2017-0009: A request to vary from the maximum allowable building height of 35 feet by 10 additional feet to construct the proposed distribution warehouse facility to a maximum building height of 45 feet.
Body
APPLICANT:
CDREP, LLC, 523 Main Street, El Segundo, CA 90245.
LOCATION:
The project site consists of three (3) parcels of land (APNs: 1133-201-01, -02 and -03) located at the northeast corner of Locust Avenue and Vineyard Avenue (Refer to the attached Location Map (Exhibit A)).
BACKGROUND:
Surrounding Land Use and Zoning
Location
Existing Land Use
Zoning
Site
SFR / Vacant
Planned Industrial (I-PID)
North
SFR
Planned Industrial (I-PID)
East
Vacant Land
Not a Part
South
Storage yard
Planned Industrial (I-PID)
West
Roof Manufacturer
General Manufacturing (I-GM)
General Plan Designations
Location
General Plan Designation
Site
Light Industrial with Specific Plan Overlay
North
Light Industrial with Specific Plan Overlay
East
N/A
South
Light Industrial with Specific Plan Overlay
West
General Industrial with Specific Plan Overlay
Site Characteristics
The project site is a rectangular shaped piece of land comprised of three (3) parcels. The project site is 5.78 net acres in size with approximate dimensions of 618 feet (east-west) by 408 feet (north-south). The project site is on the east side by Locust Avenue and north side of Vineyard Avenue. To the north are non-...