Title: Focused Traffic Impact Analysis - Construction of Expansion of Truck Parking for Old Dominion Trucking on Willow at the northwest Corner of Willow and Santa Ana Avenues. (ACTION ITEM)
Attachments: 1. Attachment 1 - Project Location Map.pdf, 2. Attachment 2 - Site Plan.pdf, 3. Attachment 3 - Proposed Project Trip Generation.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
For Transportation Commission Meeting [May 6, 2020]
TO: Honorable Chairperson and Commission
APPROVAL: Savat Khamphou, Public Works Director/City Engineer
FROM: Gene R. Klatt, Consultant Engineer, Lockwood Engineering

Title
Focused Traffic Impact Analysis - Construction of Expansion of Truck Parking for Old Dominion Trucking on Willow at the northwest Corner of Willow and Santa Ana Avenues.
(ACTION ITEM)

Body
BACKGROUND:
On May 20, 2019, the first scoping agreement was submitted for the proposed expansion of the truck parking area south of the existing Old Dominion Trucking facility on the west side of Willow Avenue between Slover and Santa Ana Avenues. On October 7, 2019, the 1st TIA was submitted, reviewed and comments prepared. A 2nd TIA was submitted January 27, 2020. A 3rd TIA was submitted March11, 2020. The project proposed is the construction of an expansion parking area with spaces for 324 truck trailers and 51 passenger car spaces on vacant land south of the existing warehouse.

The site location is shown on Page 3 of the TIA in Figure 1, which is included as Attachment 1, while the site plan is shown on Page 4 in Figure 2 of the TIA, which is included as Attachment 2. The site is at the northwest corner of Willow and Santa Ana Avenues south of the existing warehouse and parking lot.

The project is expanding into an undeveloped site south of the existing facility and will access Willow Avenue with a single driveway approximately 250 feet north of Santa Ana Avenue.

The trip impacts were estimated using data from the existing facility on a proportional basis. Trips per parking space were calculated on the existing facility and proportionally estimated based on the number of parking spaces in the proposed expansion. Trips are shown on Page 18 Table 4 of the TIA, which is included as Attachment 3. Total daily trips from this development are estimated at 1,062 PCE trips with the AM/PM peak hour being 60/55 trips. These numbers are for just the...